Create a network and substation

Create and preview a substation assembly, validate its connections, then publish it for explicit review. Original changes only after reviewed human Apply.

Before you begin

Open Create network in the project navigator. Work in an isolated editable project. Choose a source basis: supplied engineering data or a clearly labelled synthetic example. Unknown nameplate values remain unresolved.

Configure and preview

  • Template: choose single busbar, double busbar, ring bus, breaker-and-half or transformer node. The thumbnail describes an assembly; the Preview shows the native equipment that will actually be created.
  • Configuration: enter the station name, voltage levels and feeder counts. Review source, transformer and switch defaults; changing the template must not silently overwrite reviewed values.
  • Preview: select equipment in the native single-line or mapping schedule. Verify terminal connections, bus sections and normal/open positions.
  • Validation: inspect every error and warning. A missing voltage, duplicate identity or unresolved connection prevents publication. A topology check is not an interruption-duty or protection study.
  • Finish: review the generated objects and publish the complete transaction. Save the project file explicitly afterward.

Example and units

A fictional primary station can have a 132 kV incoming side, a 33 kV bus and two outgoing feeders. Native P is MW, Q is MVAr, branch rating is MVA and switch current is kA. These example values are assumptions, not manufacturer data.

Recovery

Back retains entered values. Cancel leaves the native model unchanged. A stale-source failure preserves the draft: inspect the current saved head and reconcile before retrying. Never click Finish repeatedly while a request is unresolved.

Next: Switchgear controls, Import a project, Review candidate changes.