Synthetic planning example. Numerical agreement is not engineering approval.
For companies/startups planning AI infrastructure: what reinforcement is needed when total facility demand grows from 60 MW to 100 MW? Industry relevance is a project-selection criterion; controversy does not justify unsupported environmental, financial or reliability claims.
| Configuration | MW | Normal min pu | Normal max % | Worst outage pu | Worst outage % | Outages within limits |
|---|---|---|---|---|---|---|
| Existing · 2 × 80 MVA | 60 | 0.986064 | 38.747 | 0.969255 | 78.688 | 13/13 |
| Expanded · 2 × 80 MVA | 100 | 0.975119 | 65.223 | 0.941021 | 134.639 | 9/13 |
| Expanded · 2 × 125 MVA | 100 | 0.983952 | 41.376 | 0.964312 | 84.159 | 13/13 |
| Expanded · 3 × 80 MVA | 100 | 0.984192 | 43.219 | 0.974966 | 65.234 | 15/15 |
The unchanged 100 MW supply converges normally, but its worst outage (Incoming circuit B out) reaches 134.639% and 0.941021 pu minimum. A successful normal load flow is not adequate evidence for expansion. Two 125 MVA transformers: 13/13 outages within the stated limits. Three 80 MVA transformers: 15/15. These are capacity-screening alternatives, not a least-cost recommendation; no construction or operating costs were supplied.
132/33 kV, 100 MVA base, 50 Hz. Four dual-fed aggregate hall buses, two MV sections and an explicitly closed steady-state bus tie. One shared upstream utility equivalent: incoming paths are NOT independent utility supplies. 60 MW = 48 MW IT +12 MW auxiliaries; 100 MW =80+20 MW. All loads are constant PQ at assumed 0.98 lagging PF. The overhead ratio is a snapshot assumption, not measured annual PUE. Every value is synthetic, including ratings. Transformer device-base R=.005 pu and X=.12 pu are converted to the 100 MVA system base. The complete input JSONs state line/tie impedances and ratings; no manufacturer capability is inferred. Normal and outage criteria: voltage .95–1.05 pu; continuous MVA rating ≤100%. No emergency allowance, hidden curtailment, tap optimisation or unmodeled protection transfer. The bounded utility surrogate is not a real physical generator specification.
58 normal/outage states use retained native saved-study receipts. Each is matched against the existing isolated pandapower 3.5.5 reference. Native nodal P/Q balance tolerance is 1e-4 MVA. Cross-solver tolerances: 1e-5 pu magnitude, 1e-5 rad relative angle, 1e-3 MVA terminal complex power. No disagreement is averaged away. Saved normal studies use NR tolerance1e-8/max50, no solver fallback, fixed transformer taps. Outage studies use their admitted native profile; their exact effective options are retained in the report JSON. Reopening and capture do not recalculate the results.
No real customer/site/utility data, engineering certification, UPS/battery model, transient AI-load response, harmonics, protection coordination, interconnection approval, full N-1 security or uninterrupted-service claim. Upstream utility failure, generator outages and common-mode failures are not covered. No cost, annual energy, carbon, water or regional grid-adequacy claim. A passing numerical check establishes agreement for matched equations; synthetic parameters remain unqualified for an actual installation.
Context: IEA (2025), Energy and AI, https://www.iea.org/reports/energy-and-ai/energy-demand-from-ai . Global projections do not determine the campus inputs. Model and scenarios are original synthetic examples. No third-party customer model or vendor screenshot is distributed. PowerSystem/VeraGrid and the independent reference retain their own software licenses; no runtime or installer is included. Included reproduction scripts are PowerSystem source under GPL-3.0-only; see LICENSE.txt. This package does not include the numerical libraries or their runtime installations.
Raw solver/native receipts, exact inputs, comparison quantities and original actual-app screenshots are retained. Harness-only failures are preserved in the private delivery evidence; successful native calculations were resumed by identity, not silently replayed.